Middleton Methodist Church Conversion Phase 2
Phase 2 of the works for Middleton Methodist Church, including flat renovation along with the old stage removal and refurbishment.
LOCATION: Middleton-in-Teesdale, Co Durham
COMPLETED: 2018
Phase 2 works was to strip out the remains part of the old school room the stage, toilet and porch.
These needed to be carefully stripped out lowered down and the cellar part filled up, this included adding on an additional underfloor heating zone and concreting the floor.
Additional electrics added to from tails left from phase one, there was stud walls and ceilings fitted along with windows and doors.
Finished off with floor coverings and decoration to match phase 1.
Including in this phase was refurbishment of the flat above the new Pathway.